The processing of work related costs throughout MET/TEAM is calculated when the Work Order is returned. The table below explains the hierarchy used for the calculations, the formulas, and several examples.

Funding Calculation Hierarchy

1. Kind of Job Number

2. Customer Hourly Rate * Work Order Labor (if charged)

3. Service Facility Hourly Rate * Work Order Labor (if charged)

Job Number = Standard Hours Formula

 if(JN="Standard Hours",(SP*AQ),0) + (if(OHR<>0, if(WLHC="Y", OHR*WLH,0),if(WLHC="Y", SHR*WLH,0)))+ if(ISOB="Y",ISO,0) + (WOPQ*WOPP)
Note: Once labor is added to the Work Order, the cost does not change when the Customer hourly rate or Service Facility hourly rate changes. The labor must be removed if the calculation of the labor cost is incorrect and a new labor entry created. If an expedite fee is charged, it is per asset.

Job Number = Level of Effort Formula

 if(JN="Level of Effort",0,(SP*AQ)) + (if(OHR<>0, if(WLHC="Y", OHR*WLH,0),if(WLHC="Y", SHR*WLH,0))) + if(ISOB="Y",ISO,0) +(WOPQ*WOPP)
Note: Once labor is added to the Work Order, the cost does not change when the Customer hourly rate or Service Facility hourly rate changes. The labor must be removed if the calculation of the labor cost is incorrect and a new labor entry created. If an expedite fee is charged, it is per asset.

Funding Attributes

Job Number = Standard Hours. No associated std. price, hourly rates, or labor.

Job Number = Standard Hours. Std. price exists, no hourly rate or labor. ISO fee exists not used.

Job Number = Standard Hours. Std. price exists, no hourly rate or labor. ISO fee exists and used.

Job Number = Standard Hours. Std. price exists, Customer hourly rate exists but no labor added to Work Order. ISO fee exists not used.

Job Number = Standard Hours. Std. price exists, Customer hourly rate exists but no labor added to Work Order. ISO fee exists and used.

Kind of Job Number (JN)

Standard Hours

Standard Hours

Standard Hours

Standard Hours

Standard Hours

Type Procedure Standard Hours (SH)

5

5

5

5

5

Type Procedure Standard Hours Type

Average

Average

Average

Average

Average

Type Procedure Std. Price (SP)

0

100

100

100

100

Asset Characteristics Quantity (AQ)

1

2

1

1

3

ISO Cert Fee (ISO)

0

225

225

225

225

Customer Hourly Rate (OHR)

0

0

0

50

50

Service Facility Hourly Rate (SHR)

0

0

0

0

0

Work Order ISOCert Checked (ISOB)

N

N

Y

N

Y

Work Order Labor Hours (WLH)

0

0

0

0

0

Charge Work Order Labor (WLHC)

N/A

N/A

N/A

N/A

N/A

Work Order Parts Qty (WOPQ)

0

0

0

0

0

Work Order Parts Price (WOPP)

0

0

0

0

0

Returning Cost (RC)

 $                                                   -  

 $                                                200

 $                                                325

 $                                               100

 $                                              525

Comments

Job Number = Standard Hours. Std. price exists, Customer hourly rate exists, labor added to Work Order but not charged. ISO fee exists not used.

Job Number = Standard Hours. Std. price exists, Customer hourly rate exist labor added to Work Order but not charged. ISO fee exists and used.

Job Number = Standard Hours. Std. price exists, Customer hourly rate exist labor added to Work Order and charged. ISO fee exists not used.

Job Number = Standard Hours. Std. price exists, Customer hourly rate exist labor added to Work Order and charged. ISO fee exists and used.

Job Number = Standard Hours. Std. price exists, Customer hourly rate exists, labor added to Work Order and charged. Parts added to Work Order. ISO fee exists not used.

Kind of Job Number (JN)

Standard Hours

Standard Hours

Standard Hours

Standard Hours

Standard Hours

Type Procedure Standard Hours (SH)

5

5

5

5

5

Type Procedure Standard Hours Type

Average

Average

Average

Average

Average

Type Procedure Std. Price (SP)

100

100

100

100

100

Asset Characteristics Quantity (AQ)

1

3

1

2

1

ISO Cert Fee (ISO)

225

225

225

225

225

Customer Hourly Rate (OHR)

50

50

50

50

50

Service Facility Hourly Rate (SHR)

0

0

0

0

0

Work Order ISOCert Checked (ISOB)

N

Y

N

Y

N

Work Order Labor Hours (WLH)

2.5

2.5

2.5

2.5

2.5

Charge Work Order Labor (WLHC)

N

N

Y

Y

Y

Work Order Parts Qty (WOPQ)

0

0

0

0

4

Work Order Parts Price (WOPP)

0

0

0

0

3.25

Returning Cost (RC)

 $                                                100

 $                                                525

 $                                                225

 $                                               550

 $                                              238

Comments

Job Number = Standard Hours. Std. price exists, Customer hourly rate exist labor added to Work Order and charged. Service Facility hourly rate added but no labor entered at that rate. Parts removed from Work Order. ISO fee exists not used.

Job Number = Standard Hours. Std. price exists, Customer hourly rate removed. Previous labor on Work Order at Customer's previous hourly rate; charged. Service Facility hourly rate added but no labor entered at that rate. ISO fee exists Not used.

Job Number = Standard Hours. Std. price exists, Customer hourly rate removed. Previous labor on Work Order removed. Service Facility hourly rate exists but no labor entered at that rate. ISO fee exists not used.

Job Number = Standard Hours. Std. price exists, Customer hourly rate doesn't exist. Service Facility hourly rate exists and labor entered and charged at Service Facility rate. ISO fee exists not used.

Job Number = Standard Hours. Std. price exists, Customer hourly rate doesn't exist. Service Facility hourly rate exists and labor entered and charged at Service Facility rate. Part added to Work Order. ISO fee exists not used.

Kind of Job Number (JN)

Standard Hours

Standard Hours

Standard Hours

Standard Hours

Standard Hours

Type Procedure Standard Hours (SH)

5

5

5

5

5

Type Procedure Standard Hours Type

Average

Average

Average

Average

Average

Type Procedure Std. Price (SP)

100

100

100

100

100

Asset Characteristics Quantity (AQ)

2

1

3

1

1

ISO Cert Fee (ISO)

225

225

225

225

225

Customer Hourly Rate (OHR)

50

0

0

0

0

Service Facility Hourly Rate (SHR)

75

75

75

75

75

Work Order ISOCert Checked (ISOB)

N

N

N

N

N

Work Order Labor Hours (WLH)

2.5

2.5

0

3

3

Charge Work Order Labor (WLHC)

Y

Y

N/A

Y

Y

Work Order Parts Qty (WOPQ)

0

0

0

0

8

Work Order Parts Price (WOPP)

0

0

0

0

3.25

Returning Cost (RC)

 $                                                325

 $                                                225

 $                                                300

 $                                               325

 $                                              351

Comments

Job Number = Level of Effort. Standard Hours and Std. Price exists have no effect. ISO fee exists not used.

Job Number = Level of Effort. Standard Hours and Std. Price exists have no effect. Customer hourly rate exists, labor is added to the Work Order and charged. Service Facility hourly rate added but no labor entered at that rate. ISO fee exists not used.

Job Number = Level of Effort. Standard Hours and Std. Price exists have no effect. Customer hourly rate does not exist. Service Facility hourly rate exists and labor entered on Work Order at that rate. ISO fee exists not used.

Job Number = Level of Effort. Standard Hours and Std. Price exists have no effect. Customer hourly rate exists. Service Facility hourly rate exists. Labor entered on Work Order uses Customer hourly rate. Parts added to Work Order and charged. ISO fee exists not used.

Job Number = Level of Effort. Standard Hours and Std. Price exists have no effect. Customer hourly rate exists. Service Facility hourly rate exists. Labor entered on Work Order uses Customer hourly rate. Parts added to Work Order and charged. ISO fee exists and used.

Kind of Job Number (JN)

Level of Effort

Level of Effort

Level of Effort

Level of Effort

Level of Effort

Type Procedure Standard Hours (SH)

5

6

5

5

5

Type Procedure Standard Hours Type

Average

Average

Average

Average

Average

Type Procedure Std. Price (SP)

100

100

100

100

100

Asset Characteristics Quantity (AQ)

2

1

3

1

1

ISO Cert Fee (ISO)

225

225

225

225

225

Customer Hourly Rate (OHR)

0

50

0

50

50

Service Facility Hourly Rate (SHR)

0

75

75

75

75

Work Order ISOCert Checked (ISOB)

N

N

N

N

Y

Work Order Labor Hours (WLH)

0

1

1

1

1

Charge Work Order Labor (WLHC)

N/A

Y

Y

Y

Y

Work Order Parts Qty (WOPQ)

0

0

0

8

8

Work Order Parts Price (WOPP)

0

0

0

3.25

3.25

Returning Cost (RC)

 $                                                   -  

 $                                                  50

 $                                                  75

 $                                                 76

 $                                              301

Top of Page